Project Number | PK0105 |
Program | PARKS |
Total Budget | $43,830,945 |
Estimated Start Date | Winter 2015 |
Estimated Completion Date | Summer 2017 |
Project Contact |
Meghan Tiernan, Facilities Development Manager 925-833-6630 |
This project provides for the design and construction of the first phase of a Recreation and Aquatic Complex in Emerald Glen Park. The project is known as The Wave. Design was completed in December 2014 and construction began in April 2015. Completion of The Wave is expected in mid-2017.
The Wave includes a 31,940 square-foot facility with a community room; an indoor pool for lessons, and lap swimming; an outdoor competitive pool for water polo and swimming; a children’s play pool with slide and sprays, and a slide tower with high speed slides and loop slides. Phase I also includes additional park acreage, a plaza and an amphitheater.
CITY COUNCIL ACTION(S)
City Counsel Meeting February 3, 2015 – Award Construction Contract
OTHER INFORMATION
Frequently Asked Questions regarding the Recreation & Aquatic Complex