Project Number | ST0815 |
Program | STREETS |
Total Budget | $1,413,648 |
Project Contact | William Lai |
This project provides for various improvements along Amador Plaza Road between Dublin Boulevard and Amador Valley Boulevard. The project is a tier 1 priority project in the City of Dublin Bicycle and Pedestrian Master Plan.
The project has two phases. On December 6, 2016, the City Council accepted the first phase of improvements, which included the installation of two mid-block crosswalks with pedestrian warning lights and construction of a raised concrete median at the southern Safeway/Dublin Place driveway. The second phase will include construction of an exclusive right turn lane on Amador Plaza Road at Dublin Boulevard. Phase 2 design began in mid-2017.
The General Fund was used as a means to begin the project work. It is anticipated that the Western Dublin TIF and other funding sources could cover this General Fund allocation.
CITY COUNCIL ACTION(S)